Dry powder mortar equipment test heavy load, commissioning to meet the conditions
First, the electrical (instrument) control and control systems and instrumentation adjustment test.
Second, lubrication, gas (steam) dynamic inspection and adjustment test.
Third, the mechanical and the system to adjust the joint test.
Fourth, the empty load test run, should be in the above one to three adjustment test after passing.
Dry powder mortar production line of the electrical system to meet the conditions can be debugged:
First, according to the electrical schematic diagram and the installation wiring diagram, the equipment internal wiring and external wiring should be correct.
Second, according to the type of power, grade and capacity, check or debug its cut capacity, fuse capacity, overvoltage, undervoltage, overcurrent protection, inspection or debugging content should meet its requirements.
Third, according to the equipment manual The electrical system adjustment method and debugging requirements, with the simulation operation to check the process action, instructions, signals and interlock device should be correct, sensitive and reliable.
Fourth, the above-mentioned one or three checks or adjustments, before the mechanical and the system of joint adjustment test.